Site meeting minutes template and who is responsible for what

11 min read

A site meeting is worth having if, afterwards, everyone knows what they have to do and by when. The minutes are the only thing left of the meeting, and a week later they show what actually happened. That is why the template below has little text and two action tables.

Download the template (Word)

Download the site meeting minutes template (Word)

The file is a .docx with blank fields. It has room for eight attendees, five agenda items and eight new actions; add rows when you need them.

What is in the template

The header holds the minutes number, the project, the date and time, the place, the subject, who chairs the meeting and who takes the minutes. Seven sections follow.

  1. Attendees - a table with name, company, position or role on site and a column for signatures. Below it there is a line for those who were invited but did not come.
  2. Agenda - the items for discussion, written down before the meeting.
  3. Actions from the previous meeting - task, owner, due date and status: done, on track or late.
  4. Discussion by item - for each item, what was found and what was decided.
  5. Decisions and actions - exactly what gets done, who is responsible and by which date.
  6. Questions waiting on an outside decision - queries to the designer or the client, deliveries and permits, with the name of whoever is chasing them.
  7. Next meeting - date, time and place.

At the end, the person who took the minutes and the organizer sign.

Who is responsible for what

The organizer

Calls the meeting, sends the agenda in advance and chairs it. On site this is usually the project manager or the site manager from the general contractor. It is the organizer's job to start the meeting with section three of the minutes, the old actions, and not with new topics. If the meeting starts with new topics, the late actions get left for "the end", which nobody ever reaches.

The minute taker

Writes during the meeting, not afterwards from memory. Records where things stand, not who said what. When the discussion of an item ends without a decision, the minute taker asks "Who takes this on, and by when?" before the meeting moves on.

The minutes go out on the day of the meeting. Sent three days later, they no longer work as instructions.

Anyone who sees a decision recorded differently from what was agreed replies to the email while everyone still remembers the conversation. The correction goes into section three of the next minutes, with the old actions.

The action owner

Every action has one name. "Contractor and subcontractor jointly" means nobody has taken it on. When the work really belongs to two people, it is split into two actions with separate due dates.

The due date is a date. "By the end of the week" and "as soon as possible" cannot be checked at the next meeting.

The attendees

A typical project involves the client, the supervising engineer, the designer, the general contractor and the subcontractors.

Every site meeting is attended by the contractors working on site, each with a person who can commit to a date or a delivery. A representative who only takes notes and "will check with the office" pushes every item back by a week.

The client's representative, the supervising engineer and the designer do not need to be at every meeting. Invite them when the agenda has an item that waits on their decision, and put that item first so they do not have to sit through to the end.

Whoever follows up

Between two meetings someone has to keep an eye on the due dates, otherwise a delay is only discovered at the next meeting. Usually that is the organizer. This is why section three of the template has a "Status" column with three possible answers. "In progress" is not one of them.

How to write the actions

A well written action can be understood by someone who was not at the meeting.

WeakBetter
Sort out the windows issueThe window supplier confirms in writing the delivery date for floors 3 and 4
Electrical to speed upCable pulling on floor 2 is finished before the plasterers start on Monday
Look at the leak in the basementInspection of the leak at grid line 4 in the basement, with photos and a proposed fix

Each one gets one name and one date.

In the "No." column of the template, the rows are numbered from 1 in every set of minutes. When an action is carried over to section three of the next minutes, it gets a new row number, and it helps to note in the "Task" column where it came from: "(from minutes No. 5, item 2)". With that note the action can be found in the old minutes without guessing from its wording.

For questions waiting on an outside decision, also write down since when they have been waiting. A query to the designer that has gone unanswered for three meetings in a row is already a threat to the schedule and is worth logging as a risk instead of copying it from one set of minutes to the next.

Quality issues that come up at the meeting do not stay in the minutes only. They belong on the punch list, with a photo and an assignee, so they can be checked on site later.

When an action is late

An action past its due date is not removed from the minutes. It moves to section three of the next set, and the "Due date" column keeps the original date. The new date and the reason go in the "Status" column next to "late", as the note under the table asks.

If the action is held up by someone outside the meeting (the designer, a supplier, the client), it moves to section six, with the questions waiting on an outside decision, together with the name of the person chasing it. If there is still no answer by the third meeting in a row, it is logged as a risk, like any outside query. If the new date moves other work, the risk is logged straight away, the date goes into the Gantt chart and the client is told.

In the example, at meeting No. 5 the window supplier agrees to confirm the date for floors 3 and 4 by the 10th. At No. 6 there is no confirmation, the action reads "late, new date the 17th, the supplier has not replied" and it moves to section six. At No. 7, the third in a row, there is still no answer, and the plasterers are scheduled for floor 3 on the 24th. Now the action moves the schedule: it is logged as a risk, the new plastering date goes into the Gantt chart and the client is told.

When you need a different meeting instead

Not every site topic belongs in the site meeting. The site meeting looks at how far the work has got and who takes on what until next time. How often it is held is usually set by the contract or by the project manager.

When building services routes clash with the structure, the designers and the subcontractors for each discipline get together in a coordination meeting. Design changes, payments and decisions only the client can make are discussed in a meeting with the client. Site safety measures and incidents, including those where nobody was hurt, are discussed in a separate safety meeting. Put all of that into the site meeting and it drags on, while the actions get lost between conversations about prices.

Extra work requested at the meeting

It happens that the client's representative says at the meeting "do the canopy over the entrance as well, we'll sort it out later". The request goes into the minutes, but that does not yet mean the work has been instructed. When the contract requires a written instruction and a priced change order for work outside the bill of quantities, the minutes get an action saying who prepares the change order and by when, and the canopy is built after it is signed.

What goes into the minutes and what goes into the official records

Site meeting minutes are an internal working document of the parties. They hold the actions, the owners and the due dates. They do not replace the documents that the law of the country requires for accepting covered-up work, the structure or the whole building.

The same goes for instructions. If at the meeting the designer orders a change to a detail or the supervising engineer stops work, a line in the minutes is not enough. If local law requires instructions to be recorded in an official document, for example the site diary, the instruction is recorded there too. The minutes keep an action saying who will record it and when. When a date for accepting work is agreed at the meeting and the local rules require a written notice, that notice is sent separately.

Which documents are mandatory, who signs them and how an instruction is disputed are set differently in every country.

Signed minutes still carry weight in a dispute between the parties to a contract, because they show who was told what and when. How much weight they carry in a particular case is a question for a lawyer.

The minutes in Construction Team

The actions in paper minutes stay on the page, separate from everything else on the project. In the meetings module you create the meeting with the type Site meeting, and the parts of the template have their own fields:

  • Subject, Date & time, Location, Organizer and Object make up the header.
  • Agenda is filled in when the meeting is scheduled.
  • Attendees come in two kinds: an Employee of your company or an External attendee with a name and a company. For each one you can mark whether they attended.
  • Minutes is the text of the discussion.
  • Decisions & action items are the rows with Description, Assignee and Due date.

The other meetings have their own types: Coordination, Client meeting, Safety meeting and Other. Each is a separate record, and the list of meetings can be filtered by project, type and status. Files can be attached to the meeting, for example the drawing that was discussed.

When the meeting belongs to a project, each decision becomes a project task with the action Create project task. The task stays linked to the meeting and is tracked together with the other tasks on the project. Every action from the meeting has the status Open or Done, so at the next site meeting you can see which ones are still outstanding.

A meeting goes from Scheduled to Held or Cancelled. In the actions menu, Download PDF gives you the minutes on A4 with your company letterhead: subject, date and time, type, location, project and organizer, agenda, attendees, minutes and the actions with assignee, due date and status. The attendees table has an empty column for signatures, so the sheet can be signed on site, and at the bottom are the Prepared by and Organizer fields.

An item that threatens the schedule or the budget is logged straight from the meeting with the Record as risk button, when the meeting belongs to a project.

Meetings are part of the field modules included in the Team plan and above (pricing).


Sign up for free and turn site meeting decisions into actions with an owner and a due date.

Frequently asked questions

Are site meeting minutes mandatory?

It depends on the country and on the contract. Keep them even where nobody requires them, because without minutes the decisions from the meeting cannot be followed up.

Who should take the minutes of a site meeting?

One person, chosen in advance, who is not the person chairing the meeting. Usually it is the site manager or an engineer from the general contractor's team. Whoever chairs cannot keep notes at the same time.

Should the attendees sign the minutes?

It is a good idea, especially when subcontractors and a client representative are in the room. A signature next to a name shows that the person was there and knows what was decided. That matters later, when people argue about who agreed to do what.

How detailed should the minutes be?

Short. For each agenda item, what was found and what was decided is enough. The part that matters is the action table: what gets done, by whom and by which date. A retelling of the conversation helps nobody.

Do the minutes replace the official site records?

No. When the supervising engineer or the designer gives an instruction on the works during the meeting, it is also recorded wherever the law of the country requires it, for example in the site diary where the supervisor writes instructions. The minutes only show that the instruction was given at the meeting.

Want to see the system with your own numbers?

Construction Team keeps the bill of quantities, the offer, the progress certificate and the invoice in one system, with no retyping. Answer six short questions and we will show you how.